Scope of Works
TURNPIKE SYNERGY SDN. BHD. (hereinafter referred to as the "Employer") have been appointed by PROJEK LINTASAN SUNGAI BESI - ULU KLANG SDN. BHD (hereinafter referred as "Concession Company") to carry out the purpose of the construction of the Projek Penswastaan Lebuhraya Bertingkat Sungai Besi - Ulu Kelang (SUKE).
General
-
General Description of The Expressway
The Projek Penswastaan Lebuhraya Bertingkat Sungai Besi - Ulu Kelang (SUKE) will be on elevated Expressway with mainline starting from the existing Shah Alam Highway (KESAS) ay Bukit Jalil in the South to Middle Ring Road 2 (MRR2) at Ulu Kelang in the North. The significant highlights of the expressway are as follows:
- Three lane dual carriageway
- 90 percent of the main alignment will be on elevated structure
- 1 mainline, 3 ramps
-
Main Features of the Projek Penswastaan Lebuhraya Bertingkat Sungai Besi - Ulu Kelang (SUKE)
The Project's scope of works shall include but not limited to the following:-
- Site Clearing
- Earthworks
- Ground and Slope Treatment
- Environmental Management Plan & Erosion Sediment and Control Plan
- Road Drainage System
- Bore Pile and Caisson Piles
- Bridge works - Precast and Cast In-situ, Segmental Box Girder, Beam and Slab, Precast and Cast In-situ Crosshead.
- Geotechnical Works
- Culverts - New, extension and replacement
- Rigid Pavement
- Flexible Pavement - New, Widening, Overlaying and Resurfacing
- Road Marking and Road Furniture
- Protection and Relocation of Services
- Traffic Diversion and Traffic Management Plan
- Landscape Works
- Routine Maintenance for Existing Road
Related Works by Others
There are other contactors, sub-contractors or suppliers who may be appointed / designated by the Employer to carry out works in the same or adjacent areas. It is of paramount importance that the execution of the Works is fully and completely coordinated with the related Works which are carried out by others and coordinated by the Employer.
Other Info
- Approximate length = 3.20km (CH. 21200.00 to CH. 24000.00)
- Contract Period = 30 months
- Site Possession Date = 29th August 2016
- Actual Completion Date = 26th July 2021
- Defect Liability Period (DLP) = 24 months